August 29, 2024: View looking East towards Yonge from Hillsdale.
May 28, 2024: UOVO has topped off the structural form with the waterproofing assembly in place. Erection of precast and windows continues to close in the building form.
November 13, 2023: Precast Work Well Underway
September 21, 2023: 12-storey building form revealing the East and South Elevations, with Precast panels erected on the southeast side
Septmeber 20, 2023: Canopy steel work complete facing East onto Yonge Street with a wrap around at the corner to Hillsdale Avenue
Precast panels have arrived on-site with erection starting on the South Elevation
First concrete pour to gain access to below grade now complete
Septmeber 12, 2023: Preparation of the twelfth level, with rebar and conduit work on-going
Outdoor amenity area on the second level looking West
Ramp to below grade, with rebar in place, ready for concrete pour
July 2, 2023: Structural form of UOVO at the corner of Yonge Street and Hillsdale Avenue
June 19, 2023: Currently Forming Level 7
January 31, 2023: Second pour of level 2 complete
January 24, 2023: Verticals from level 2 to level 3
January 16, 2023: Level 2 pour 1 complete
January 9, 2023: Rebar placement complete on level 2
January 5, 2023: Formwork extended up to Level 2
November 3, 2022: Formwork now on the second level
September 23, 2022: Forming verticals on ground floor slab
August 17, 2022: Preparing for second pour of ground floor
July 22, 2022: preparing to pour the ground floor slab
July 18, 2022: preparation of verticals from p1 to grade
June 28, 2022: preparation of verticals from p1 to grade
April 4, 2022: pouring p2 slab
March 22, 2022: ready to pour p2 slab
Febraury 1, 2022: in preparation of forming p3 slab
November 10, 2021: in preparation of the raft slab
October 20, 2021: crane now erected
September 16, 2021: mud mat complete - waterproofing started
August 11, 2021: excavation continues to bottom of raft slab
July 20, 2021: now on P4 level
June 25, 2021: starting excavation of P3
April 16, 2021: excavation and dewatering continues
January 12, 2021: preparation for dewatering started
December 5, 2020
November 25, 2020: shoring work is now 50% completed
September 28, 2020: guide walls completed. shoring work to begin next
August 21, 2020: overhead protection for pedestrians initiated as we prepare for shoring
July 28, 2020: prepping for removal of TTC retaining wall
september 15, 2019
August 14, 2019
june 27, 2019
x | view from Hillsdale looking south
x | view from Hillsdale looking south
x | view from Hillsdale looking south west
x | view from site looking south
x | view from site looking south west
x | view from site looking south east
x | view from site looking south east
x | view from site looking south west
x | view from site looking west
x | view from bridge looking south
x | view from site looking south east
x | view from site looking south
x | view from hillsdale ave looking south west
x | view from site looking south east
x | view from hillsdale ave looking south east
x | view from site looking south east
x | view from site looking east
x | view from site looking south
x | view from site looking west
x | view from site looking north east
x | view from site looking north
x | view from site looking east
x | view from site looking south west
x | view from site looking south west
x | view from site looking north
x | view from site looking west
x | view from site looking south
x | view from site looking south
x | view from site looking south east
x | view from site looking south west
x | view from site looking north
x | view from site looking west
x | view from site looking south east
x | view from site looking north
x | view from site looking north west
x | view from site looking north east
x | view from site looking south east
x | view from site looking south west
x
x | view from site looking west
x | view looking into site
x | view from site looking north east
x | crane now erected
x | crane now erected
x | in preparation of the raft slab
x | in preparation of the raft slab
x | in preparation of the raft slab
x | structural columns and walls completed on p4
x | in preparation of forming p3 slab
x | in preparation of forming p3 slab
x | Ready to Pour P2 Slab
x | Pouring P2 Slab
x | Preparation of verticals from P1 to Grade
x | Preparation of verticals from P1 to Grade
x | Preparation of verticals from P1 to Grade
x | Preparation of verticals from P1 to Grade
x | Preparation of verticals from P1 to Grade
x | Preparation of verticals from P1 to Grade
x | Preparing to Pour the Ground Floor Slab
x | Preparing to Pour the Ground Floor Slab
x | Preparing to Pour the Ground Floor Slab
x | Preparing for Second Pour of Ground Floor
x | Preparing for Second Pour of Ground Floor
x | Preparing for Second Pour of Ground Floor
x | View Facing West
x | Forming Verticals on Ground Floor Slab
x | South View Working on Verticals
x | Formwork now on the second level
x | Formwork now on the second level
x | Formwork now on the second level
x | Formwork extended up to Level 2
x | View looking northeast
x | View looking southeast
x | Rebar placement complete on level 2
x
x
x | Level 2 pour 1 complete - View looking northwest
x | Level 2 pour 1 complete - View looking northeast
x | Level 2 pour 1 complete - View looking east
x | Verticals from level 2 to level 3 - View looking southeast
x | Verticals from level 2 to level 3 - View looking west along Hillsdale
x | South wall, form ready for second lift of pour 2 - View looking southeast
x | Second pour of level 2 complete - View looking northeast
x | Second pour of level 2 complete - View looking east
x | Second pour of level 2 complete - View looking southeast
x | Currently Forming Level 7
x | Currently Forming Level 7
x | Currently Forming Level 7
x | Structural form of UOVO at the corner of Yonge Street and Hillsdale Avenue
x | Currently decking and pouring on 8th level, view looking southeast
x | View along Hillsdale Avenue, showing height of retail and entrance to parking ramp on the west side
x | ????????
x | ????????
x | ????????
x | Preparation of the twelfth level, with rebar and conduit work on-going
x | Outdoor amenity area on the second level looking West
x | Ramp to below grade, with rebar in place, ready for concrete pour
x | Canopy steel work complete facing East onto Yonge Street with a wrap around at the corner to Hillsdale Avenue
x | Precast panels have arrived on-site with erection starting on the South Elevation
x | First concrete pour to gain access to below grade now complete
x | 12-storey building form revealing the East and South Elevations, with Precast panels erected on the southeast side
x | View looking South, showcasing the building form along Yonge Street
x | View looking East, revealing the West Elevation of UOVO Residences
x | Precast Work Well Underway
x | Precast Work Well Underway
x | Precast Work Well Underway
x | UOVO has topped off the structural form with the waterproofing assembly in place. Erection of precast and windows continues to close in the building form.
x | UOVO has topped off the structural form with the waterproofing assembly in place. Erection of precast and windows continues to close in the building form.
x | UOVO has topped off the structural form with the waterproofing assembly in place. Erection of precast and windows continues to close in the building form.
x | View looking East towards Yonge from Hillsdale.