UOVO
Now Under Construction
uovo
floorplans
gallery
davisville
team
registration
contact
construction update
uovo
floorplans
gallery
davisville
team
registration
contact
construction update
Now Under Construction
construction update
January 31, 2023: Second pour
of level 2 complete
January 24, 2023: Verticals from
level 2 to level 3
January 18, 2023: Forming verticals from level 2 to level 3
January 16, 2023: Level 2 pour 1 complete
January 9, 2023: Rebar placement complete on level 2
January 5, 2023: Formwork extended up to Level 2
November 3, 2022: Formwork now on the second level
September 23, 2022: Forming verticals on ground floor slab
August 17, 2022:
Preparing for second pour of ground floor
July 22, 2022:
preparing to pour the ground floor slab
July 18, 2022:
preparation of verticals from p1 to grade
June 28, 2022:
preparation of verticals from p1 to grade
June 16, 2022:
p1: pour 1 and pour 2 complete
April 4, 2022:
pouring p2 slab
March 22, 2022:
ready to pour p2 slab
March 16, 2022:
p2 decking underway
March 10, 2022:
80% of p3 floor forming complete
March 7, 2022
march 4, 2022:
additional slab pour on p3 complete
preparation for concrete pour at tie back location
March 4, 2022:
additional slab pour on p3 complete
March 4, 2022:
preparation for concrete pour at
tie back location
March 1, 2022:
forming work continues on p3
Febraury 1, 2022:
in preparation of forming p3 slab
November 10, 2021:
in preparation of the raft slab
October 20, 2021:
crane now erected
September 29, 2021:
prep for crane erection
september 29, 2021:
prep for crane erection
october 20, 2021: crane now erected
September 16, 2021: mud mat complete - waterproofing started
August 27, 2021: preparation for raft slab pour
August 25, 2021
August 11, 2021: excavation continues to bottom of raft slab
July 30, 2021: hoist installation underway
July 20, 2021: now on P4 level
June 25, 2021: starting excavation of P3
June 7, 2021: excavation continues, approaching 2nd row of tie backs
April 16, 2021: excavation and dewatering continues
January 12, 2021: preparation for dewatering started
December 5, 2020
November 25, 2020: shoring work is now 50% completed
September 28, 2020: guide walls completed. shoring work to begin next
August 21, 2020: overhead protection for pedestrians initiated as we prepare for shoring
July 28, 2020: prepping for removal of TTC retaining wall
September 20, 2019: back filling completed, in preparation of drill rig equipment for shoring work to begin
september 15, 2019
August 14, 2019
July 2, 2019
june 27, 2019
x
| view from construction site looking south west
x
| view from construction site looking south east
x
| view from construction site looking south
x
| view from construction site looking south west
x
| view from construction site looking north west
x
| view from construction site looking south west
x
| view from construction site looking south
x
| view from construction site looking south
x
| view from Hillsdale looking south
x
| view from Hillsdale looking south
x
| view from Hillsdale looking south west
x
| aerial view looking south
x
| view from construction site looking south west
x
| view from Hillsdale looking south
x
| view from Hillsdale looking south
x
| view from Hillsdale looking south east
x
| view from Hillsdale looking south east
x
| view from Hillsdale looking south west
x
| view from Yonge looking north west
x
| view from site looking east
x
| view from yonge looking south west
x
| view from Yonge looking north west
x
| view from the corner of yonge & Hillsdale looking south west
x
| view from site looking south
x
| view from site looking south west
x
| view from site looking south east
x
| view from site looking north
x
| view from site looking north east
x
| view from site looking south east
x
| view from site looking south east
x
| view from site looking south west
x
| view from site looking west
x
| view from site looking north
x
| view from site looking west
x
| view from site looking south west
x
| view from site looking south east
x
| view from site looking south west
x
| view from site looking south
x
| view from site looking south
x
| view from site looking south
x
| view from site looking south east
x
| view from site looking south
x
| view from site looking south
x
| view from bridge looking south
x
| view from site looking south east
x
| view from site looking south
x
| view from site looking south west
x
| view from site looking south
x
| view from site looking south
x
| view from site looking north
x
| exposed footing of the retaining wall
x
| view from site looking north
x
| west side of the property showing u-fill and saw cut of retaining wall
x
| south side of the property looking west
x
| south side of the property looking east
x
| south side of the property looking south west
x
| view from site looking north east
x
| view from site looking north west
x
| view from hillsdale ave looking south west
x
| view from site looking south east
x
| view from hillsdale ave looking south east
x
| view from site looking south east
x
| view from site looking west
x
| view from site looking south
x
| view from site looking north
x
| view from site looking south
x
| view from site looking north east
x
| view from site looking north east
x
| view from site looking north east
x
| view from site looking north east
x
| view from site looking south east
x
| view from site looking east
x
| view from site looking south
x
| Steel Flange for King Piles
x
| Drilling Rig Positioned on the East Side Along Yonge
x
| Pouring a Filer Pile on the East Side
x
| view from site looking north
x
| view from site looking north east
x
| view from site looking east
x
| view from site looking west
x
| view from site looking north east
x
| view from site looking north
x
| view from site looking south west
x
| view from site looking south
x
| view from site looking north west
x
| view from site looking east
x
| view from site looking south west
x
| view from site looking south west
x
| view from site looking north west
x
| view from site looking south west
x
| view from site looking west
x
| view from site looking north
x
| view from site looking west
x
| view from site looking south
x
| view from site looking north east
x
| view from site looking east
x
| view from site looking south
x
| view from site looking south
x
| view from site looking south east
x
| view from site looking south west
x
| view from site looking north west
x
| view from site looking north
x
| view from site looking south west
x
| showing the dewatering system and west side of site
x
| view looking south showing the level of excavation on the site
x
| cutting back the caisson wall on the south side looking west
x
| looking north east revealing cross braces at the south west corner
x
| view looking west
x
| view from site looking north west
x
| view from site looking north west
x
| view from site looking south west
x
| view from site looking east
x
| view from site looking north east
x
| view from site looking east
x
| view from site looking north
x
| view from site looking north
x
| view from site looking west
x
| view from site looking south east
x
| view from site looking north
x
| view from site looking north west
x
| view from site looking north east
x
| view from site looking north west
x
| view from site looking north west
x
| view from site looking north west
x
| view from site looking south east
x
| view from site looking south west
x
x
| view from site looking south east
x
| view from site looking north east
x
x
| view from site looking south east
x
| view from site looking north west
x
| view from site looking south
x
| view from site looking west
x
| view looking into site
x
| view from site looking north east
x
| view from site looking north
x
| crane now erected
x
| crane now erected
x
| in preparation of the raft slab
x
| in preparation of the raft slab
x
| in preparation of the raft slab
x
| structural columns and walls completed on p4
x
| in preparation of forming p3 slab
x
| in preparation of forming p3 slab
x
| Forming work continues on P3
x
| Additional Slab Pour on P3 Complete
x
| Preparation for Concrete Pour at Tie Back Location
x
x
| 80% of P3 Floor Forming Complete
x
| P2 Decking Underway
x
| Ready to Pour P2 Slab
x
| Pouring P2 Slab
x
| Pour 1 and Pour 2 Complete for P1
x
| Pour 1 and Pour 2 Complete for P1
x
| Preparation of verticals from P1 to Grade
x
| Preparation of verticals from P1 to Grade
x
| Preparation of verticals from P1 to Grade
x
| Preparation of verticals from P1 to Grade
x
| Preparation of verticals from P1 to Grade
x
| Preparation of verticals from P1 to Grade
x
| Preparing to Pour the Ground Floor Slab
x
| Preparing to Pour the Ground Floor Slab
x
| Preparing to Pour the Ground Floor Slab
x
| Preparing for Second Pour of Ground Floor
x
| Preparing for Second Pour of Ground Floor
x
| Preparing for Second Pour of Ground Floor
x
| View Facing West
x
| Forming Verticals on Ground Floor Slab
x
| South View Working on Verticals
x
| Formwork now on the second level
x
| Formwork now on the second level
x
| Formwork now on the second level
x
| Formwork extended up to Level 2
x
| View looking northeast
x
| View looking southeast
x
| Rebar placement complete on level 2
x
x
x
| Level 2 pour 1 complete - View looking northwest
x
| Level 2 pour 1 complete - View looking northeast
x
| Level 2 pour 1 complete - View looking east
x
| Verticals from level 2 to level 3 - View looking southeast
x
| Verticals from level 2 to level 3 - View looking west along Hillsdale
x
| South wall, form ready for second lift of pour 2 - View looking southeast
x
| Second pour of level 2 complete - View looking northeast
x
| Second pour of level 2 complete - View looking east
x
| Second pour of level 2 complete - View looking southeast