Now Under Construction

construction update
click to enlarge

November 13, 2023: Precast Work Well Underway
Uovo Construction Update
Uovo Construction Update
Uovo Construction Update
September 21, 2023: 12-storey building form revealing the East and South Elevations, with Precast panels erected on the southeast side
Uovo Construction Update
Uovo Construction Update
Uovo Construction Update
Septmeber 20, 2023: Canopy steel work complete facing East onto Yonge Street with a wrap around at the corner to Hillsdale Avenue
Uovo Construction Update
Precast panels have arrived on-site with erection starting on the South Elevation
Uovo Construction Update
First concrete pour to gain access to below grade now complete
Uovo Construction Update
Septmeber 12, 2023: Preparation of the twelfth level, with rebar and conduit work on-going
Uovo Construction Update
Outdoor amenity area on the second level looking West
Uovo Construction Update
Ramp to below grade, with rebar in place, ready for concrete pour
Uovo Construction Update
July 2, 2023: Structural form of UOVO at the corner of Yonge Street and Hillsdale Avenue
Uovo Construction Update
Uovo Construction Update
Uovo Construction Update
June 19, 2023: Currently Forming Level 7
Uovo Construction Update
Uovo Construction Update
Uovo Construction Update
January 31, 2023: Second pour of level 2 complete
Uovo Construction Update
Uovo Construction Update
Uovo Construction Update
January 24, 2023: Verticals from level 2 to level 3
Uovo Construction Update
Uovo Construction Update
Uovo Construction Update
January 16, 2023: Level 2 pour 1 complete
Uovo Construction Update
Uovo Construction Update
Uovo Construction Update
January 9, 2023: Rebar placement complete on level 2
Uovo Construction Update
Uovo Construction Update
Uovo Construction Update
January 5, 2023: Formwork extended up to Level 2
Uovo Construction Update
Uovo Construction Update
Uovo Construction Update
November 3, 2022: Formwork now on the second level
Uovo Construction Update
Uovo Construction Update
Uovo Construction Update
September 23, 2022: Forming verticals on ground floor slab
Uovo Construction Update
Uovo Construction Update
Uovo Construction Update
August 17, 2022: Preparing for second pour of ground floor
Uovo Construction Update
Uovo Construction Update
Uovo Construction Update
July 22, 2022: preparing to pour the ground floor slab
Uovo Construction Update
Uovo Construction Update
Uovo Construction Update
July 18, 2022: preparation of verticals from p1 to grade
Uovo Construction Update
Uovo Construction Update
Uovo Construction Update
June 28, 2022: preparation of verticals from p1 to grade
Uovo Construction Update
Uovo Construction Update
Uovo Construction Update
April 4, 2022: pouring p2 slab
Uovo Construction Update
March 22, 2022: ready to pour p2 slab
Uovo Construction Update
Febraury 1, 2022: in preparation of forming p3 slab
Uovo Construction Update
Uovo Construction Update
Uovo Construction Update
November 10, 2021: in preparation of the raft slab
Uovo Construction Update
Uovo Construction Update
Uovo Construction Update
October 20, 2021: crane now erected
Uovo Construction Update
Uovo Construction Update
September 16, 2021: mud mat complete - waterproofing started
Uovo Construction Update
Uovo Construction Update
Uovo Construction Update
August 11, 2021: excavation continues to bottom of raft slab
Uovo Construction Update
Uovo Construction Update
Uovo Construction Update
July 20, 2021: now on P4 level
Uovo Construction Update
Uovo Construction Update
Uovo Construction Update
June 25, 2021: starting excavation of P3
Uovo Construction Update
Uovo Construction Update
Uovo Construction Update
April 16, 2021: excavation and dewatering continues
Uovo Construction Update
Uovo Construction Update
Uovo Construction Update
January 12, 2021: preparation for dewatering started
Uovo Construction Update
Uovo Construction Update
Uovo Construction Update
December 5, 2020
Uovo Construction Update
Uovo Construction Update
Uovo Construction Update
November 25, 2020: shoring work is now 50% completed
Uovo Construction Update
Uovo Construction Update
Uovo Construction Update
September 28, 2020: guide walls completed. shoring work to begin next
Uovo Construction Update
Uovo Construction Update
Uovo Construction Update
August 21, 2020: overhead protection for pedestrians initiated as we prepare for shoring
Uovo Construction Update
Uovo Construction Update
Uovo Construction Update
July 28, 2020: prepping for removal of TTC retaining wall
Uovo Construction Update
Uovo Construction Update
Uovo Construction Update
september 15, 2019
Uovo Construction Update
Uovo Construction Update
Uovo Construction Update
August 14, 2019
Uovo Construction Update
Uovo Construction Update
Uovo Construction Update
june 27, 2019
Uovo Construction Update
Uovo Construction Update
Uovo Construction Update
x | view from Hillsdale looking south
x | view from Hillsdale looking south
x | view from Hillsdale looking south west
x | view from site looking south
x | view from site looking south west
x | view from site looking south east
x | view from site looking south east
x | view from site looking south west
x | view from site looking west
x | view from bridge looking south
x | view from site looking south east
x | view from site looking south
x | view from hillsdale ave looking south west
x | view from site looking south east
x | view from hillsdale ave looking south east
x | view from site looking south east
x | view from site looking east
x | view from site looking south
x | view from site looking west
x | view from site looking north east
x | view from site looking north
x | view from site looking east
x | view from site looking south west
x | view from site looking south west
x | view from site looking north
x | view from site looking west
x | view from site looking south
x | view from site looking south
x | view from site looking south east
x | view from site looking south west
x | view from site looking north
x | view from site looking west
x | view from site looking south east
x | view from site looking north
x | view from site looking north west
x | view from site looking north east
x | view from site looking south east
x | view from site looking south west
x
x | view from site looking west
x | view looking into site
x | view from site looking north east
x | crane now erected
x | crane now erected
x | in preparation of the raft slab
x | in preparation of the raft slab
x | in preparation of the raft slab
x | structural columns and walls completed on p4
x | in preparation of forming p3 slab
x | in preparation of forming p3 slab
x | Ready to Pour P2 Slab
x | Pouring P2 Slab
x | Preparation of verticals from P1 to Grade
x | Preparation of verticals from P1 to Grade
x | Preparation of verticals from P1 to Grade
x | Preparation of verticals from P1 to Grade
x | Preparation of verticals from P1 to Grade
x | Preparation of verticals from P1 to Grade
x | Preparing to Pour the Ground Floor Slab
x | Preparing to Pour the Ground Floor Slab
x | Preparing to Pour the Ground Floor Slab
x | Preparing for Second Pour of Ground Floor
x | Preparing for Second Pour of Ground Floor
x | Preparing for Second Pour of Ground Floor
x | View Facing West
x | Forming Verticals on Ground Floor Slab
x | South View Working on Verticals
x | Formwork now on the second level
x | Formwork now on the second level
x | Formwork now on the second level
x | Formwork extended up to Level 2
x | View looking northeast
x | View looking southeast
x | Rebar placement complete on level 2
x
x
x | Level 2 pour 1 complete - View looking northwest
x | Level 2 pour 1 complete - View looking northeast
x | Level 2 pour 1 complete - View looking east
x | Verticals from level 2 to level 3 - View looking southeast
x | Verticals from level 2 to level 3 - View looking west along Hillsdale
x | South wall, form ready for second lift of pour 2 - View looking southeast
x | Second pour of level 2 complete - View looking northeast
x | Second pour of level 2 complete - View looking east
x | Second pour of level 2 complete - View looking southeast
x | Currently Forming Level 7
x | Currently Forming Level 7
x | Currently Forming Level 7
x | Structural form of UOVO at the corner of Yonge Street and Hillsdale Avenue
x | Currently decking and pouring on 8th level, view looking southeast
x | View along Hillsdale Avenue, showing height of retail and entrance to parking ramp on the west side
x | ????????
x | ????????
x | ????????
x | Preparation of the twelfth level, with rebar and conduit work on-going
x | Outdoor amenity area on the second level looking West
x | Ramp to below grade, with rebar in place, ready for concrete pour
x | Canopy steel work complete facing East onto Yonge Street with a wrap around at the corner to Hillsdale Avenue
x | Precast panels have arrived on-site with erection starting on the South Elevation
x | First concrete pour to gain access to below grade now complete
x | 12-storey building form revealing the East and South Elevations, with Precast panels erected on the southeast side
x | View looking South, showcasing the building form along Yonge Street
x | View looking East, revealing the West Elevation of UOVO Residences
x | Precast Work Well Underway
x | Precast Work Well Underway
x | Precast Work Well Underway